Capacity and performance ratio tests are essential tools used to showcase the efficiency of photovoltaic (PV) plants to potential buyers or lenders, helping de-risk their investment. These tests provide a clear, data-driven comparison between the expected and actual system performance, ensuring that the plant operates as modeled—within acceptable margins of error.
One widely recognized standard is ASTM E2848-13, "Standard Test Method for Reporting Photovoltaic Non-Concentrator System Performance." This test evaluates how closely the real-world performance of a PV system aligns with its modeled predictions. The goal is to confirm that the system performs as expected, accounting for normal uncertainties. By following a well-defined, standardized process managed by a committee, this test ensures consistency, transparency, and quality across different projects.
**Why does this matter for project owners and financiers?**
Failure to meet the test criteria or delays in completing it can have serious financial implications. For instance, liquidated damages (LDs) may be triggered if the system doesn’t perform as promised. This makes the test a critical milestone at the end of the development and construction phase.
**How is the test conducted?**
Although the concept seems simple, the process involves detailed calculations and careful data handling. Here's a step-by-step breakdown:
**Step 1 – Gather Inputs**
To avoid delays, make sure you have all the necessary components ready:
- A validated PVSYST model.
- Experience in regression modeling and access to a test sheet.
- A fully operational system with properly functioning equipment and calibrated weather stations.
- At least 5–7 days of continuous operation, though weather conditions may affect this timeline.
**Step 2 – Export Data**
Collect and prepare the data for analysis:
- Extract annual raw data from PVSYST, including GHI irradiance, ambient temperature, wind speed, POA correction factors, and timestamps.
- Export climate and performance data from your data acquisition system, including date/time, production meter readings, temperature, wind speed, and POA irradiance.
- Review mechanical and electrical drawings to identify any issues like shading or inverter clipping that could impact results.
**Step 3 – Filter Data for Quality**
This is often the most challenging part of the test. Ensure the data meets the following minimum requirements:
- At least 50 fifteen-minute data points (or 750 minutes of data).
- Exclude data below 400 W/m² and ensure the system operates above 98% of the inverter’s nameplate capacity.
- Keep POA irradiance within ±20% of the reported value.
- While there are no strict limits on temperature or wind, exclude outliers that don't correlate with performance.
**Step 4 – Run the Regression**
Perform a regression analysis to calculate the power capacity and standard error. If the measured power divided by the modeled power is greater than 95%, and the regression error is under 5%, the test is considered successful.
If results aren’t satisfactory, common issues include:
- Delays in gathering enough high-quality data due to weather or system design.
- Using summary reports instead of raw data from PVSYST.
- Improper regression setup, even when following ASTM guidelines.
- Poorly calibrated sensors, which can significantly affect accuracy.
**Who conducts these complex tests?**
Pure Power has an Owners Engineering team specialized in ASTM E2848 and other performance testing protocols. As an independent third party, we conduct the analysis thoroughly and objectively, ensuring compliance with industry standards and providing reliable, actionable insights for project stakeholders.